What an ALTA Survey Utilities Review Can Reveal Before Redevelopment

Old sites hide a lot underground. A former shopping plaza, warehouse, or office park may have decades of water lines, sewer laterals, gas services, and buried cables, many of them poorly documented. An ALTA survey utilities review gives developers and buyers a mapped picture of what serves the property, what crosses it, and which rights other parties hold. Getting that picture before you finalize plans can save a redesign, a delayed permit, or an expensive surprise once the excavator shows up.
Existing Utility Conditions on the Property
An ALTA survey shows the utilities a surveyor can see and document on the property. Under the minimum standards, the surveyor records observed evidence such as manholes, valves, hydrants, meters, poles, transformers, and pipe outlets. That evidence tells you where service enters the site and how lines likely run.
Table A Item 11 goes further, and it’s often the most useful add-on for redevelopment. Item 11(a) shows utilities based on plans or reports the client provides plus what the surveyor observes in the field. Item 11(b) adds markings from a utility locate request, such as an 811 call. Your lender may require one of these, but a developer often benefits from ordering 11(b) even when it’s optional.
Keep the limits in mind. Locate markings are approximate, and public locate services usually don’t mark private lines like site lighting, irrigation, or a private storm system. If your design depends on exact depths or positions, ask about subsurface utility engineering or test pits as a separate service.
Utility Easements and Recorded Rights
A utility easement is a recorded right that lets a company or agency run, maintain, or access lines on your land. The ALTA survey plots easements listed in the title commitment when the documents describe a location that can be mapped. It also notes visible evidence of utilities that don’t match any recorded easement.
That mismatch is worth your attention. A sewer main crossing the middle of a lot with no recorded easement raises title and access questions you’ll want answered early. On the other hand, an old easement on paper may cover a line that was abandoned years ago, and getting it released could open up usable land.
Ask your title company and attorney to review any gaps the survey flags. Release or relocation rules vary by utility provider, municipality, and county. Don’t assume an easement can be moved just because the line inside it looks unused.
Utility Conflicts That Affect Redevelopment Plans
Utility conflicts are places where existing lines or easements interfere with what you want to build. They show up most often in footprints, parking layouts, and new driveways. A building pad that sits over a water main or inside a power line easement usually has to shift, shrink, or wait for relocation.
Common conflicts found on older commercial sites include:
- Building additions planned over sewer or storm lines
- New curb cuts that cross gas services or fiber vaults
- Dumpster pads or loading docks inside an easement area
- Overhead power lines that limit building height or crane access
- Shared service lines that also feed a neighboring parcel
Each one carries a cost and a schedule impact. Relocation work often depends on the utility company’s own timeline, which you can’t control. Finding conflicts before site plan approval gives you room to adjust the design rather than paying for changes later.
Survey Data for Coordinating Site Improvements
The utility data in an ALTA survey becomes a working base for your design team. Civil engineers use it to plan new connections, size services, and route storm drainage. Architects use it to set building footprints that stay clear of easements.
Ask for the survey in a digital format your engineers can use, such as CAD files, along with the signed plat. Confirm the horizontal and vertical datum so everyone works from the same reference. If you also need contours or spot grades, adding a topographic survey with Table A Item 5 keeps the utility and grade data in one coordinated drawing.
Contractors benefit too. Clear utility mapping helps with bid accuracy, demolition planning, and later construction staking. Fewer unknowns usually mean fewer change orders.
Using Utility Findings During Project Due Diligence
Use the utility findings to test whether the deal still works. Compare the mapped lines and easements against your concept plan, your budget, and your lender’s requirements. If major relocation is needed, factor that cost and timing into the purchase price or contract terms.
Order the survey early in the due diligence period. Records research, locate requests, and title review all take time, and late findings leave little room to negotiate. Survey needs can vary by lender, title company, municipality, and project scope, so confirm the Table A items with everyone involved before fieldwork starts.
This is general information, not legal advice. Your attorney can advise on easement rights and contract protections. A good surveyor can tell you what the data shows and where more investigation makes sense.
Frequently Asked Questions
Does every ALTA survey show utilities?
Every ALTA survey shows observed evidence of utilities, like manholes, poles, and valves. It doesn’t automatically map underground lines between those features. Table A Item 11 adds that detail using plans, field evidence, and locate markings. Ask for Item 11 if utilities matter to your plans.
What is the difference between Table A Item 11(a) and 11(b)?
Item 11(a) relies on plans or reports you provide plus what the surveyor observes on site. Item 11(b) includes all of that and adds markings from a utility locate request. The 11(b) option usually gives a fuller picture of underground lines. It can also add time and cost to the survey.
Will an ALTA survey find private utility lines?
It may show private lines if there’s visible evidence or if you provide plans. Public locate services typically don’t mark private utilities such as site lighting or irrigation. A private locating firm can mark those lines before the survey. Mention any known private systems to your surveyor at the start.
Can a utility easement be moved for redevelopment?
Sometimes, but it depends on the utility owner, the easement terms, and local rules. Relocation often requires the provider’s approval, engineering, and a new recorded easement. The process can take months and is usually paid by the developer. Raise the question early with the provider and your attorney.
When should I order an ALTA survey with utilities?
Order it as soon as you have a signed purchase contract and a title commitment. Utility findings can change your design, budget, or deal terms. Waiting too long leaves little time to respond to problems. Early ordering also keeps your closing and permit schedule on track.